Work on the reconstruction of the rowing channel

Work on the reconstruction of the rowing channel

The head of Rostov Administration of Vitaly Kushnarev has supervised the progress of works on reconstruction of the rowing channel "Don".

All work is performed by LLC "Uzhnaya stroitelnaya companiya". Construction readiness of the facility – 30%.

Now on the rowing channel "Don" the following types of work are performed: under the dumping shoreline (East side), are constructions made of gabions SecuTech coastline (on the North side), performed the dredging work on the alignment of the bottom of the boat channel. At the facility employs 30 to 50 people.

The total cost of the project is 670 million rubles, at the moment 232,5 mln was mastered.