The Future Rostov-Arena Ticket Office Monolithic Structures Completed By 85%

The Future Rostov-Arena Ticket Office Monolithic Structures Completed By 85%

The ticket office monolithic structures of the future stadium are completed by 85%. This was told by the Minister of Construction, Architecture and Territorial Development of the Rostov region Nikolai Bezuglov.

To date, at Rostov-Arena, the laying of brick partitions is completed by 90%, the laying of external walls and partitions – by 85%, and the installation of prefabricated elements of decking – by 75%.

Plastering and electrical work, installation of sewage systems, water and heat supply of the new stadium are completed by more than 60%.

The installation of a media facade system is under way. Totally, 19.3 thousand square meters to be mounted. The installation of stained-glass windows and window blocks as well as elevators and doors is under way too.

The site around the stadium is being landscaped. A large pedestrian boulevard will be built on the west side. Around it, there will be planted trees, installed architectural compositions decorated with lighting. From the east, there will be the main pedestrian routes, the area around which will be landscaped as well. On the south side of the stadium, the main sites for disembarking passengers arriving from the Platov airport, as well as car parks and pedestrian walkways will be built.

The readiness of the Rostov-Arena is about 70%. The final deadline for completion is December 25, 2017.